It’s been a productive week.  After a last minute scramble, our 20′ storage container is on site along with all the steel, wood, fasteners, tools and talent needed to begin our forming work for the footings.  The footings are the basis of the foundation and will connect each home to the underlying bedrock.

IMG_0680

After anchoring one of the top markers for the foundation of the Tower villa,  Bruce and Shiraz are marking the exact location of the floor of the villa on scaffolding erected for each corner of the home using a laser leveling device.

IMG_0689

Using these markings as a guide, they will begin forming the footings which attach the villa to bedrock.

Villa Floor

Here’s what we’ve done so far with the light blue highlight showing what we’ve accomplished over the past week.

Site Plan 8-14-16

Next step is to finish the excavation of the 1BR house and continue to form the foundation for the ‘Tower’ villa.

Have a great Sunday!

 

 

 