The crew was focused on the pool in earnest this week as we move toward a plaster date of July 14, and pool turn up on the 15th.

IMG_8579

The pool decking is about 50% complete, and the glass work for the scum line and step delineations should be finished early this week.

IMG_8581

IMG_8576

IMG_8578

The grill/bar area is marked out and will contain a built-in grill, double sink, under- counter, double-wide refrigerator and built-in coolers, all for hosting a killer party or simply a small cookout.IMG_8605

The infinity edge is complete, but we’re waiting on 6×6 pieces to finish off the overflow tank and lap lane marker.  Hopefully it arrived on St Thomas today!

IMG_8606

The top two villas are receiving their finishing touches and polishing.  Here’s the Resysta product being applied to the upper 1BR.  It still needs to be washed off, as it is a bit dusty, but it looks beautiful and warms up this very modern design!

IMG_8610

The Tower villa received its island piece, but it still needs a few shelves!

IMG_8572

The island is made of quartz with a waterfall design. Built-in mahogany shelving will create a see through, floating-shelf effect.  A full reveal will come after it receives its shelving!

IMG_8571

Poolside villas number 1 & 2 are moving along and are waiting on some additional painting and electrical.

IMG_8614

Cami’s still in Texas, but she certainly seems to be enjoying herself!

Maybe not so much sharing the grocery cart with a big sprig of dill!

IMG_8553

But I definitely think she has the purse thing down…

Have a great week everyone!